Here’s a history of Maryville from cisterns to 102 to Mozingo and back to 102.
Humorous Overview
- Maryville voters approved up to $50 million in waterworks bonds. That’s a lot of support for a project whose main goal is making sure the water keeps flowing—and the paperwork keeps floating.
- The 1958 plant got emergency membrane replacements in 2025 and 2026. At this point, it’s had more membrane refreshes than a phone has software updates.
- The new plant’s price came in at $44.77 million, down from earlier estimates near $80 million. That’s not just cost-saving—it’s a deep discount on deep infrastructure.
- Missouri awarded a $52.5 million funding package. The plant hasn’t even opened yet, and it’s already bringing home more awards than a water-treatment reality show.
- The city approved two 50% water-rate increases. The good news: the water will be cleaner. The bad news: your wallet may need a little treatment, too.
- Groundbreaking began in November 2026. Finally, a city project where “breaking ground” is both the construction update and the beginning of a very long conversation about water bills.
- The new facility is expected to be substantially complete in July 2028, with the switch planned for fall. The old plant has had 70 years to prepare for retirement—and it still wants to stay on the shift until the new one passes inspection.
- Maryville’s water system is getting a major upgrade. Soon, the water will be new, the pipes will be ready, and the ratepayers will be saying, “I’d like a glass of water—and a glass of water-rate explanation.”
History 1845-1957

Before building its 1958 facility, Maryville’s drinking water progressed from private wells and cisterns to an 1886 private franchise waterworks on the 102 River, followed by a 1912 municipal buyout and early twentieth-century filtration upgrades.
1845–1885: Wells, Cisterns & Fire Protection Needs
- Early Household Supplies. After Maryville was laid out in 1845 above the One Hundred and Two (102) River, residents and businesses relied entirely on shallow private wells, rainwater cisterns, and hauled river water. [1]
- Growing Town & Fire Risks. As Maryville expanded into a regional trade and educational hub following the arrival of the railroad in the late 1860s and 1870s, shallow wells struggled with seasonal droughts, sanitation concerns, and the lack of pressurized water for firefighting.
1886–1911: The Private Maryville Water Company Era
- 1886 Franchise Construction. To bring pressurized water and fire hydrants to town, Maryville granted a franchise to a private utility—the Maryville Water Company—which built the city’s first piped waterworks along the 102 River east of town in 1886.
- Steam Pumping & Standpipe Distribution. Typical of late-1880s Missouri river utilities, the original works used steam-driven pumps to lift river water through settling basins and into a standpipe/elevated storage system feeding cast-iron mains downtown.
- Private-to-Public Tension. By the turn of the twentieth century, growing residential demand, the opening of what is now Northwest Missouri State University (founded 1905), and disputes over franchise rates, water clarity, and service extensions fueled calls for municipal ownership.
1912–1957: Municipal Ownership & Early River Treatment
- 1912 Municipal Buyout. In 1912, Maryville voters approved bonds to purchase the private waterworks from the Maryville Water Company, bringing water production and distribution under permanent city ownership.
- Early Filtration & Chlorination. Over the next several decades, the city modernized the 19th-century river station by adding rapid sand filtration, chemical coagulation, and continuous chlorination—eliminating waterborne disease outbreaks while handling muddy runoff from the 102 River.
- Post-WWII Capacity Strain. By the 1950s, post-war population growth, expanding university enrollment, and severe mid-1950s Midwest droughts strained both the aging 1886/1912 riverworks and the 102 River’s low-flow reliability, prompting the city to construct the modern 1958 water treatment plant on the east side along Highway 136. [1, 2]
History 1958-present

Maryville’s municipal water system has evolved from a 1958 river-fed treatment plant into a Mozingo Lake reservoir system, culminating in the $52.1 million ozone and biofiltration plant scheduled for completion in Fall 2028. [1, 2]
1958–1994: River-Era Plant & Reservoir Transition
- 1958 — Original Water Treatment Plant Built. The city constructed its existing treatment facility to draw and treat surface water from the One Hundred and Two (102) River. [1, 2]
- 1991–1992 — Mozingo Lake Constructed. Maryville built the 1,006-acre Mozingo Lake reservoir by damming Mozingo Creek to secure a drought-resilient long-term water supply. [1, 2]
- 1994 — Switch to Mozingo Lake & Plant Retrofit. Maryville transitioned its primary water source from the 102 River to Mozingo Lake. Rather than building a new lake-specific facility, the city modified the 1958 river plant and added membrane filtration. [1, 2]
2004–2024: Aging Infrastructure & Interim Fixes
- 2004, 2011, & 2020 — Recurring Membrane Replacements. Because the retrofitted membranes struggled with cold winter temperatures and seasonal lake chemistry, the city had to replace filtration membranes repeatedly at costs of hundreds of thousands of dollars per cycle. [1, 2]
- 2020–2024 — Alternatives Analysis & Pilot Testing. Facing severe algal blooms (causing geosmin/MIB taste and odor issues) and an estimated $7 million to $10 million bill to replace aging membranes by 2027, the city worked with HDR Engineering to evaluate treatment alternatives and pilot-test ozone and biological activated filtration (O3-BAF). [1, 2, 3, 4]
- 2023–2024 — Temporary Clearwell GAC Conversion. To relieve acute taste and odor complaints while designing the new plant, HDR and city crews repurposed a decommissioned 1958 clearwell into a temporary granular activated carbon (GAC) adsorber alongside seasonal lake monitoring. [1]
2025–2028: The $52.1M Plant Build & Rate Phase-In

- February 4, 2025 — Voter Bond Approval. More than 80% of Maryville voters approved up to $50 million in waterworks revenue bonds to finance the new facility.
- 2025–2026 — Emergency Membrane Maintenance. While finalizing new plant designs, the city completed emergency membrane replacements in 2025 and 2026 to keep the 1958 facility reliable.
- March – June 2026 — GMP Locked & State Funding Awarded. The city finalized a $44.77 million Guaranteed Maximum Price (GMP) with Crossland Heavy Contractors to build the plant on the existing site (cutting ~$27.9 million off earlier ~$80M greenfield estimates), and on June 9, 2026, the Missouri Department of Natural Resources officially awarded the $52.5 million funding package ($50M low-interest loan + $2.5M grant).
- October – November 2026 — Rate Ordinances & Groundbreaking. The City Council enacted consecutive 50% water rate increases for FY 2027 and FY 2028 to meet state loan revenue covenants, while active earthwork broke ground on the site in November 2026.
- January 1, 2027 — First 50% Rate Increase Takes Effect. Water rates rise 50% across city and wholesale accounts (followed by a second 50% increase on January 1, 2028).
- July – Fall 2028 — Substantial Completion & Cutover. Substantial construction is targeted for July 2028, followed by testing, DNR certification, and full switchover from the 1958 facility in Fall 2028. [1, 2, 3, 4]